58. Which technique is used to analyze trends in risk occurrence?
Trend analysis
Root cause analysis
SWOT analysis
Assumptions analysis
✅ Correct Answer: Trend analysis
59. What is the purpose of a workaround?
Respond to unanticipated risks
Reduce known risks
Transfer risks
Avoid risks
✅ Correct Answer: Respond to unanticipated risks
60. Which process involves determining which risks may affect the project?
Identify Risks
Plan Risk Management
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Identify Risks
61. What is the primary purpose of the Perform Qualitative Risk Analysis process?
Prioritize risks for further analysis
Calculate exact financial impacts
Develop risk responses
Assign risk owners
✅ Correct Answer: Prioritize risks for further analysis
62. Which technique uses expert judgment to assess risks?
Delphi technique
Monte Carlo simulation
Sensitivity analysis
Decision tree analysis
✅ Correct Answer: Delphi technique
63. What is the purpose of a risk categorization?
Group risks by common causes
Assign risk owners
Calculate risk impacts
Develop risk responses
✅ Correct Answer: Group risks by common causes
64. Which document contains historical risk information?
Organizational process assets
Project charter
Stakeholder register
Communication plan
✅ Correct Answer: Organizational process assets
65. What is the primary purpose of the Perform Quantitative Risk Analysis process?
Numerically analyze effect on objectives
Identify new risks
Assign risk owners
Develop risk management plan
✅ Correct Answer: Numerically analyze effect on objectives
66. Which technique models project outcomes under different scenarios?
Monte Carlo simulation
SWOT analysis
Root cause analysis
Assumptions analysis
✅ Correct Answer: Monte Carlo simulation
67. What is the purpose of a decision tree in risk analysis?
Evaluate options under uncertainty
Identify new risks
Assign risk owners
Categorize risks
✅ Correct Answer: Evaluate options under uncertainty
68. Which process involves developing options to enhance opportunities?
Plan Risk Responses
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Responses
69. What is the primary purpose of a contingency reserve?
Address known risks
Cover unknown risks
Increase project budget
Reduce project scope
✅ Correct Answer: Address known risks
70. Which risk response strategy seeks to increase probability of opportunity?
Enhance
Exploit
Share
Accept
✅ Correct Answer: Enhance
71. What is the purpose of a risk trigger?
Indicate risk is about to occur
Assign risk owners
Calculate risk impact
Develop risk responses
✅ Correct Answer: Indicate risk is about to occur
72. Which process involves implementing contingency plans?
Implement Risk Responses
Monitor Risks
Plan Risk Responses
Perform Qualitative Analysis
✅ Correct Answer: Implement Risk Responses
73. What is the primary purpose of the Monitor Risks process?
Track identified risks and identify new ones
Develop risk responses
Assign risk owners
Create risk management plan
✅ Correct Answer: Track identified risks and identify new ones
74. Which technique is used to analyze project vulnerabilities?
SWOT analysis
Monte Carlo simulation
Decision tree analysis
Sensitivity analysis
✅ Correct Answer: SWOT analysis
75. What is the purpose of a risk reassessment?
Identify new risks and reassess current ones
Change risk owners
Update risk management plan
Reallocate contingency reserves
✅ Correct Answer: Identify new risks and reassess current ones
76. Which document contains risk-related contractual agreements?
Project documents updates
Project charter
Stakeholder register
Communication plan
✅ Correct Answer: Project documents updates
77. What is the primary purpose of a risk audit?
Evaluate effectiveness of risk responses
Identify new risks
Assign risk owners
Update risk categories
✅ Correct Answer: Evaluate effectiveness of risk responses
78. Which technique is used to analyze causes of risks?
Root cause analysis
Trend analysis
SWOT analysis
Assumptions analysis
✅ Correct Answer: Root cause analysis
79. What is the purpose of a workaround?
Respond to unanticipated risks
Reduce known risks
Transfer risks
Avoid risks
✅ Correct Answer: Respond to unanticipated risks
80. Which process involves determining risk management approach?
Plan Risk Management
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Management
81. What is the primary purpose of the Identify Risks process?
Document potential risks
Analyze risk probability
Develop risk responses
Assign risk owners
✅ Correct Answer: Document potential risks
82. Which technique uses anonymous expert input?
Delphi technique
Brainstorming
Interviewing
Checklist analysis
✅ Correct Answer: Delphi technique
83. What is the purpose of a risk breakdown structure?
Categorize risks
Assign risk owners
Calculate risk impacts
Develop risk responses
✅ Correct Answer: Categorize risks
84. Which document contains risk thresholds?
Risk Management Plan
Project Charter
Stakeholder Register
Communication Plan
✅ Correct Answer: Risk Management Plan
85. What is the primary purpose of the Perform Qualitative Risk Analysis process?
Prioritize risks for further analysis
Calculate exact financial impacts
Develop risk responses
Assign risk owners
✅ Correct Answer: Prioritize risks for further analysis
86. Which technique uses probability distributions?
Monte Carlo simulation
SWOT analysis
Root cause analysis
Assumptions analysis
✅ Correct Answer: Monte Carlo simulation
87. What is the purpose of a sensitivity analysis?
Determine most influential risks
Measure team sensitivity
Evaluate stakeholder tolerance
Assess project complexity
✅ Correct Answer: Determine most influential risks
88. Which process involves developing risk responses?
Plan Risk Responses
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Responses
89. What is the primary purpose of a contingency reserve?
Address known risks
Cover unknown risks
Increase project budget
Reduce project scope
✅ Correct Answer: Address known risks
90. Which risk response strategy involves insurance?
Transfer
Mitigate
Avoid
Accept
✅ Correct Answer: Transfer
91. What is the purpose of a risk trigger?
Indicate risk is about to occur
Assign risk owners
Calculate risk impact
Develop risk responses
✅ Correct Answer: Indicate risk is about to occur
92. Which process involves implementing risk responses?
Implement Risk Responses
Monitor Risks
Plan Risk Responses
Perform Qualitative Analysis
✅ Correct Answer: Implement Risk Responses
93. What is the primary purpose of the Monitor Risks process?
Track identified risks and identify new ones
Develop risk responses
Assign risk owners
Create risk management plan
✅ Correct Answer: Track identified risks and identify new ones
94. Which technique is used to analyze project weaknesses?
SWOT analysis
Monte Carlo simulation
Decision tree analysis
Sensitivity analysis
✅ Correct Answer: SWOT analysis
95. What is the purpose of a risk reassessment?
Identify new risks and reassess current ones
Change risk owners
Update risk management plan
Reallocate contingency reserves
✅ Correct Answer: Identify new risks and reassess current ones
96. Which document contains risk-related contracts?
Project documents updates
Project charter
Stakeholder register
Communication plan
✅ Correct Answer: Project documents updates
97. What is the primary purpose of a risk audit?
Evaluate effectiveness of risk responses
Identify new risks
Assign risk owners
Update risk categories
✅ Correct Answer: Evaluate effectiveness of risk responses
98. Which technique is used to analyze fundamental causes?
Root cause analysis
Trend analysis
SWOT analysis
Assumptions analysis
✅ Correct Answer: Root cause analysis
99. What is the purpose of a workaround?
Respond to unanticipated risks
Reduce known risks
Transfer risks
Avoid risks
✅ Correct Answer: Respond to unanticipated risks
100. Which process involves defining risk management approach?
Plan Risk Management
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Management
101. What is the primary purpose of the Identify Risks process?
Document potential risks
Analyze risk probability
Develop risk responses
Assign risk owners
✅ Correct Answer: Document potential risks
102. Which technique uses expert judgment anonymously?
Delphi technique
Brainstorming
Interviewing
Checklist analysis
✅ Correct Answer: Delphi technique
103. What is the purpose of a risk breakdown structure?
Categorize risks
Assign risk owners
Calculate risk impacts
Develop risk responses
✅ Correct Answer: Categorize risks
104. Which document contains risk appetite levels?
Risk Management Plan
Project Charter
Stakeholder Register
Communication Plan
✅ Correct Answer: Risk Management Plan
105. What is the primary purpose of the Perform Qualitative Risk Analysis process?
Prioritize risks for further analysis
Calculate exact financial impacts
Develop risk responses
Assign risk owners
✅ Correct Answer: Prioritize risks for further analysis
106. Which technique uses statistical sampling?
Monte Carlo simulation
SWOT analysis
Root cause analysis
Assumptions analysis
✅ Correct Answer: Monte Carlo simulation
107. What is the purpose of a sensitivity analysis?
Determine most influential risks
Measure team sensitivity
Evaluate stakeholder tolerance
Assess project complexity
✅ Correct Answer: Determine most influential risks
108. Which process involves creating risk response plans?
Plan Risk Responses
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Responses
109. What is the primary purpose of a contingency reserve?
Address known risks
Cover unknown risks
Increase project budget
Reduce project scope
✅ Correct Answer: Address known risks
110. Which risk response strategy involves contractual transfer?
Transfer
Mitigate
Avoid
Accept
✅ Correct Answer: Transfer
111. What is the purpose of a risk trigger?
Indicate risk is about to occur
Assign risk owners
Calculate risk impact
Develop risk responses
✅ Correct Answer: Indicate risk is about to occur
112. Which process involves executing risk response plans?
Implement Risk Responses
Monitor Risks
Plan Risk Responses
Perform Qualitative Analysis
✅ Correct Answer: Implement Risk Responses
113. What is the primary purpose of the Monitor Risks process?
Track identified risks and identify new ones
Develop risk responses
Assign risk owners
Create risk management plan
✅ Correct Answer: Track identified risks and identify new ones
114. Which technique is used to analyze organizational weaknesses?
SWOT analysis
Monte Carlo simulation
Decision tree analysis
Sensitivity analysis
✅ Correct Answer: SWOT analysis
115. What is the purpose of a risk reassessment?
Identify new risks and reassess current ones
Change risk owners
Update risk management plan
Reallocate contingency reserves
✅ Correct Answer: Identify new risks and reassess current ones
116. Which document contains risk-related agreements?
Project documents updates
Project charter
Stakeholder register
Communication plan
✅ Correct Answer: Project documents updates
117. What is the primary purpose of a risk audit?
Evaluate effectiveness of risk responses
Identify new risks
Assign risk owners
Update risk categories
✅ Correct Answer: Evaluate effectiveness of risk responses
118. Which technique is used to analyze underlying causes?
Root cause analysis
Trend analysis
SWOT analysis
Assumptions analysis
✅ Correct Answer: Root cause analysis
119. What is the purpose of a workaround?
Respond to unanticipated risks
Reduce known risks
Transfer risks
Avoid risks
✅ Correct Answer: Respond to unanticipated risks
120. Which process involves establishing risk management methodology?
Plan Risk Management
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Management
121. What is the primary purpose of the Identify Risks process?
Document potential risks
Analyze risk probability
Develop risk responses
Assign risk owners
✅ Correct Answer: Document potential risks
122. Which technique uses anonymous expert consensus?
Delphi technique
Brainstorming
Interviewing
Checklist analysis
✅ Correct Answer: Delphi technique
123. What is the purpose of a risk breakdown structure?
Categorize risks
Assign risk owners
Calculate risk impacts
Develop risk responses
✅ Correct Answer: Categorize risks
124. Which document contains risk tolerance levels?
Risk Management Plan
Project Charter
Stakeholder Register
Communication Plan
✅ Correct Answer: Risk Management Plan
125. What is the primary purpose of the Perform Qualitative Risk Analysis process?
Prioritize risks for further analysis
Calculate exact financial impacts
Develop risk responses
Assign risk owners
✅ Correct Answer: Prioritize risks for further analysis
126. Which technique uses random sampling?
Monte Carlo simulation
SWOT analysis
Root cause analysis
Assumptions analysis
✅ Correct Answer: Monte Carlo simulation
127. What is the purpose of a sensitivity analysis?
Determine most influential risks
Measure team sensitivity
Evaluate stakeholder tolerance
Assess project complexity
✅ Correct Answer: Determine most influential risks
128. Which process involves developing risk response strategies?
Plan Risk Responses
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Responses
129. What is the primary purpose of a contingency reserve?
Address known risks
Cover unknown risks
Increase project budget
Reduce project scope
✅ Correct Answer: Address known risks
130. Which risk response strategy involves outsourcing?
Transfer
Mitigate
Avoid
Accept
✅ Correct Answer: Transfer
131. What is the purpose of a risk trigger?
Indicate risk is about to occur
Assign risk owners
Calculate risk impact
Develop risk responses
✅ Correct Answer: Indicate risk is about to occur
132. Which process involves carrying out risk response plans?
Implement Risk Responses
Monitor Risks
Plan Risk Responses
Perform Qualitative Analysis
✅ Correct Answer: Implement Risk Responses
133. What is the primary purpose of the Monitor Risks process?
Track identified risks and identify new ones
Develop risk responses
Assign risk owners
Create risk management plan
✅ Correct Answer: Track identified risks and identify new ones
134. Which technique is used to analyze internal weaknesses?
SWOT analysis
Monte Carlo simulation
Decision tree analysis
Sensitivity analysis
✅ Correct Answer: SWOT analysis
135. What is the purpose of a risk reassessment?
Identify new risks and reassess current ones
Change risk owners
Update risk management plan
Reallocate contingency reserves
✅ Correct Answer: Identify new risks and reassess current ones
136. Which document contains risk-related contracts?
Project documents updates
Project charter
Stakeholder register
Communication plan
✅ Correct Answer: Project documents updates
137. What is the primary purpose of a risk audit?
Evaluate effectiveness of risk responses
Identify new risks
Assign risk owners
Update risk categories
✅ Correct Answer: Evaluate effectiveness of risk responses
138. Which technique is used to analyze fundamental reasons?
Root cause analysis
Trend analysis
SWOT analysis
Assumptions analysis
✅ Correct Answer: Root cause analysis
139. What is the purpose of a workaround?
Respond to unanticipated risks
Reduce known risks
Transfer risks
Avoid risks
✅ Correct Answer: Respond to unanticipated risks
140. Which process involves defining how to conduct risk management?
Plan Risk Management
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Management
141. What is the primary purpose of the Identify Risks process?
Document potential risks
Analyze risk probability
Develop risk responses
Assign risk owners
✅ Correct Answer: Document potential risks
142. Which technique uses expert judgment without attribution?
Delphi technique
Brainstorming
Interviewing
Checklist analysis
✅ Correct Answer: Delphi technique
143. What is the purpose of a risk breakdown structure?
Categorize risks
Assign risk owners
Calculate risk impacts
Develop risk responses
✅ Correct Answer: Categorize risks
144. Which document contains risk thresholds?
Risk Management Plan
Project Charter
Stakeholder Register
Communication Plan
✅ Correct Answer: Risk Management Plan
145. What is the primary purpose of the Perform Qualitative Risk Analysis process?
Prioritize risks for further analysis
Calculate exact financial impacts
Develop risk responses
Assign risk owners
✅ Correct Answer: Prioritize risks for further analysis
146. Which technique uses probability distributions?
Monte Carlo simulation
SWOT analysis
Root cause analysis
Assumptions analysis
✅ Correct Answer: Monte Carlo simulation
147. What is the purpose of a sensitivity analysis?
Determine most influential risks
Measure team sensitivity
Evaluate stakeholder tolerance
Assess project complexity
✅ Correct Answer: Determine most influential risks
148. Which process involves creating risk response strategies?
Plan Risk Responses
Identify Risks
Perform Qualitative Analysis
Monitor Risks
✅ Correct Answer: Plan Risk Responses
149. What is the primary purpose of a contingency reserve?
Address known risks
Cover unknown risks
Increase project budget
Reduce project scope
✅ Correct Answer: Address known risks
150. Which risk response strategy involves insurance policies?
Transfer
Mitigate
Avoid
Accept
✅ Correct Answer: Transfer
The Pmi Rmp Pmi Risk Management Professional certification is a globally recognized credential for IT professionals.
This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.
Want more practice? Check out our other mock exams: