Pmi Ca0 001 Certified Associate In Project Management Practice Test - Set 1

Test your knowledge with this Pmi Ca0 001 Certified Associate In Project Management mock exam. Get real-world IT questions and prepare for certification success.

CA0-001: Certified Associate in Project Management (CAPM) Certification - Exam Information

Exam Information

Exam Code

Pmi Ca0 001 Certified Associate In Project Management

Exam Title

CA0-001: Certified Associate in Project Management (CAPM) Certification

Vendor

PMI

Difficulty

Beginner

Duration

3 Hours

Question Format

Multiple Choice

Last Updated

February 24, 2025

The CA0-001 exam is designed for entry-level project managers looking to gain CAPM certification.

Practice Test

Shop Best CA0-001: Certified Associate in Project Management (CAPM) Certification Resources Worldwide Amazon

1. What is the primary purpose of a project charter?

Authorize the project
Define the project schedule
Identify project risks
Create the project budget

2. Which document formally defines how a project will be executed and monitored?

Project Management Plan
Project Charter
Work Breakdown Structure
Scope Statement

3. Which project management process group focuses on completing project work?

Executing
Initiating
Planning
Monitoring and Controlling

4. Which project management knowledge area includes risk identification?

Project Risk Management
Project Scope Management
Project Cost Management
Project Stakeholder Management

5. What is a Work Breakdown Structure (WBS) used for?

Breaking down project deliverables into smaller tasks
Estimating project costs
Identifying project stakeholders
Creating the project charter

6. Which scheduling method helps identify the longest path of dependent tasks?

Critical Path Method
Program Evaluation and Review Technique (PERT)
Gantt Chart
Rolling Wave Planning

7. What is the purpose of a risk register?

To document identified project risks
To track stakeholder communication
To estimate project costs
To create a project schedule

8. What document outlines project roles, responsibilities, and authority levels?

Responsibility Assignment Matrix
Project Charter
Work Breakdown Structure
Scope Statement

9. Which stakeholder has the authority to approve project changes?

Project Sponsor
Project Manager
Team Members
Customers

10. What is the primary output of the Identify Stakeholders process?

Stakeholder Register
Communication Plan
Project Charter
Risk Register

11. Which document details the work required to complete a project?

Scope Statement
Project Charter
Risk Register
Quality Management Plan

12. Which project constraint is directly affected by a schedule delay?

Time
Scope
Quality
Cost

13. Which process is part of the Monitoring and Controlling process group?

Control Scope
Develop Project Charter
Acquire Resources
Define Activities

14. What is the main purpose of a lessons learned document?

To document project successes and failures
To identify project stakeholders
To create the project budget
To define project deliverables

15. Which technique is commonly used for estimating project costs?

Analogous Estimating
Pareto Analysis
Ishikawa Diagram
Monte Carlo Simulation

16. Which process involves ensuring that project deliverables meet quality standards?

Control Quality
Plan Quality Management
Manage Quality
Validate Scope

17. Which document lists all project work and deliverables?

Work Breakdown Structure
Project Schedule
Risk Register
Change Log

18. What is the primary benefit of stakeholder engagement?

Increased project success
Reduced project scope
Lower project costs
Shorter project timelines

19. What is the primary function of the Change Control Board (CCB)?

Approve or reject project changes
Define the project scope
Monitor project resources
Create the project schedule

20. Which project management tool helps visualize project timelines?

Gantt Chart
Pareto Chart
Ishikawa Diagram
Control Chart

21. What is the primary output of the Develop Project Charter process?

Project Charter
Project Management Plan
Stakeholder Register
Requirements Document

22. Which process involves determining which quality standards are relevant to the project?

Plan Quality Management
Control Quality
Manage Quality
Validate Scope

23. What does EVM stand for in project management?

Earned Value Management
Expected Value Measurement
Estimated Variance Method
Efficiency Verification Matrix

24. Which document formally authorizes a new project or phase?

Project Charter
Business Case
Project Management Plan
Scope Statement

25. What is the purpose of a milestone in project scheduling?

To mark significant events
To allocate resources
To identify risks
To track costs

26. Which knowledge area includes processes for identifying and managing project stakeholders?

Project Stakeholder Management
Project Communications Management
Project Resource Management
Project Integration Management

27. What is the main purpose of the Monitor and Control Project Work process?

To track project performance
To execute project activities
To develop the project charter
To close the project

28. Which technique is used to identify potential risks?

Brainstorming
Critical Path Method
Earned Value Analysis
Pareto Chart

29. What is the purpose of a communication management plan?

To define how information will be distributed
To identify project risks
To create the WBS
To estimate costs

30. Which process involves obtaining seller responses and selecting sellers?

Conduct Procurements
Plan Procurement Management
Control Procurements
Close Procurements

31. What is the primary purpose of the Perform Integrated Change Control process?

To review and approve/reject changes
To identify changes
To implement changes
To document changes

32. Which document defines how project scope will be verified and controlled?

Scope Management Plan
Project Charter
WBS
Requirements Document

33. What does SPI (Schedule Performance Index) measure?

Schedule efficiency
Cost efficiency
Quality performance
Risk exposure

34. Which process involves finalizing all project activities?

Close Project or Phase
Monitor and Control Project Work
Direct and Manage Project Work
Develop Project Charter

35. What is the purpose of a responsibility assignment matrix (RAM)?

To define roles and responsibilities
To track project costs
To schedule activities
To manage quality

36. Which process involves developing an approximation of the monetary resources needed?

Estimate Costs
Determine Budget
Control Costs
Plan Cost Management

37. What is the main purpose of the Validate Scope process?

To formalize acceptance of deliverables
To control changes to scope
To define scope
To create WBS

38. Which document contains approved project changes?

Change Log
Project Charter
WBS
Risk Register

39. What is the purpose of a stakeholder analysis?

To identify stakeholder interests and influence
To estimate project costs
To create the project schedule
To define quality standards

40. Which process involves tracking team member performance?

Manage Team
Acquire Resources
Develop Team
Plan Resource Management

41. Which contract type provides the seller with payment for actual costs plus a fixed fee?

Cost Plus Fixed Fee
Fixed Price
Time and Materials
Purchase Order

42. What is the purpose of a kick-off meeting?

To align stakeholders on project objectives
To create the WBS
To develop the project charter
To identify all risks

43. Which process involves determining what to procure and when?

Plan Procurement Management
Conduct Procurements
Control Procurements
Close Procurements

44. What does TCPI (To-Complete Performance Index) indicate?

Future cost performance needed
Current schedule performance
Quality metrics
Risk probability

45. Which leadership style is most effective for motivated, competent teams?

Delegating
Directing
Supporting
Coaching

46. What is the purpose of a fishbone diagram?

Identify root causes of problems
Track project schedule
Estimate costs
Assign resources

47. Which process involves establishing policies for quality management?

Plan Quality Management
Manage Quality
Control Quality
Validate Scope

48. What does OBS stand for in project management?

Organizational Breakdown Structure
Operational Budget System
Official Baseline Schedule
Objective Benchmarking Standard

49. Which technique helps prioritize risks?

Probability and Impact Matrix
SWOT Analysis
Pareto Chart
Control Chart

50. What is the primary purpose of a project management office (PMO)?

Standardize project governance
Execute projects
Develop project charters
Control quality

51. Which document defines how requirements will be collected and managed?

Requirements Management Plan
Scope Statement
Project Charter
WBS

52. What is the purpose of a control chart in quality management?

Monitor process stability
Identify root causes
Prioritize risks
Track schedule

53. Which process involves improving team competencies?

Develop Team
Acquire Resources
Manage Team
Plan Resource Management

54. What is the main output of the Define Activities process?

Activity List
Project Schedule
WBS
Milestone Chart

55. Which technique is used to estimate activity durations?

Three-Point Estimating
Pareto Analysis
Ishikawa Diagram
Monte Carlo Simulation

56. What is the purpose of a stakeholder engagement assessment matrix?

Track stakeholder engagement levels
Assign project roles
Estimate costs
Create WBS

57. Which process involves obtaining necessary team members?

Acquire Resources
Develop Team
Manage Team
Plan Resource Management

58. What is the main purpose of a quality audit?

Identify process improvements
Inspect deliverables
Estimate costs
Assign resources

59. Which document defines how changes will be managed?

Change Management Plan
Project Charter
WBS
Risk Register

60. What is the primary purpose of a bidder conference?

Ensure common understanding among sellers
Select vendors
Negotiate contracts
Terminate contracts

61. Which process involves creating formal acceptance of project deliverables?

Validate Scope
Control Scope
Define Scope
Create WBS

62. What is the purpose of a Pareto chart?

Identify most significant factors
Show process stability
Display project schedule
Track resources

63. Which technique is used to resolve conflicts?

Collaborating
Avoiding
Smoothing
Forcing

64. What is the main output of the Plan Risk Responses process?

Risk Response Plan
Risk Register
Risk Breakdown Structure
Probability and Impact Matrix

65. Which document defines how resources will be acquired and managed?

Resource Management Plan
Project Charter
WBS
Schedule

66. What is the purpose of a make-or-buy analysis?

Decide whether to produce internally or purchase
Select vendors
Estimate costs
Assign resources

67. Which process involves distributing information to stakeholders?

Manage Communications
Plan Communications
Monitor Communications
Identify Stakeholders

68. What is the primary purpose of a stakeholder register?

Document stakeholder information
Track project costs
Create schedule
Manage quality

69. Which technique is used to forecast project performance?

Trend Analysis
Root Cause Analysis
Ishikawa Diagram
Pareto Chart

70. What is the main purpose of a lessons learned register?

Document knowledge gained during project
Track risks
Estimate costs
Assign resources

71. Which process involves implementing risk response plans?

Implement Risk Responses
Plan Risk Management
Identify Risks
Monitor Risks

72. What is the purpose of a weighted scoring model?

Evaluate project selection criteria
Estimate costs
Assign resources
Track schedule

73. Which document defines how configuration items will be managed?

Configuration Management Plan
Change Management Plan
Project Charter
WBS

74. What is the primary purpose of a quality checklist?

Verify required steps are completed
Identify risks
Estimate costs
Assign resources

75. Which technique is used to analyze project constraints?

What-if Analysis
Pareto Analysis
Ishikawa Diagram
Control Chart

76. What is the purpose of a stakeholder engagement plan?

Manage stakeholder expectations
Track costs
Create schedule
Assign resources

77. Which process involves monitoring procurement performance?

Control Procurements
Plan Procurement Management
Conduct Procurements
Close Procurements

78. What is the main purpose of a requirements documentation?

Describe project and product requirements
Track costs
Create schedule
Assign resources

79. Which technique is used to collect requirements?

Interviews
Pareto Analysis
Control Charts
Ishikawa Diagrams

80. What is the primary purpose of a project closure report?

Document final project status
Initiate new project
Identify risks
Estimate costs

81. Which process involves completing procurement activities?

Close Procurements
Control Procurements
Conduct Procurements
Plan Procurement Management

82. What is the purpose of a risk audit?

Evaluate effectiveness of risk responses
Identify new risks
Estimate costs
Assign resources

83. Which document defines how schedule will be developed and controlled?

Schedule Management Plan
Project Charter
WBS
Risk Register

84. What is the primary purpose of a communications matrix?

Define communication requirements
Track costs
Create schedule
Assign resources

85. Which technique is used to optimize the project schedule?

Resource Leveling
Pareto Analysis
Control Charts
Ishikawa Diagrams

86. What is the purpose of a work performance report?

Provide project status information
Initiate project
Identify risks
Estimate costs

87. Which process involves implementing approved changes?

Direct and Manage Project Work
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase

88. What is the primary purpose of a procurement statement of work?

Describe procurement items in detail
Track costs
Create schedule
Assign resources

89. Which technique is used to analyze project variances?

Variance Analysis
Pareto Analysis
Control Charts
Ishikawa Diagrams

90. What is the purpose of a project governance framework?

Define decision-making processes
Track costs
Create schedule
Assign resources

91. Which process involves verifying that deliverables meet requirements?

Control Quality
Manage Quality
Plan Quality Management
Validate Scope

92. What is the purpose of a responsibility assignment matrix (RAM)?

Define who does what work
Track costs
Create schedule
Manage quality

93. Which document defines how costs will be estimated and controlled?

Cost Management Plan
Project Charter
WBS
Risk Register

94. What is the primary purpose of a risk breakdown structure?

Categorize identified risks
Track costs
Create schedule
Assign resources

95. Which technique is used to analyze project performance?

Earned Value Management
Pareto Analysis
Control Charts
Ishikawa Diagrams

96. What is the purpose of a project scope statement?

Define project deliverables and work
Track costs
Create schedule
Assign resources

97. Which process involves monitoring stakeholder engagement?

Monitor Stakeholder Engagement
Identify Stakeholders
Plan Stakeholder Engagement
Manage Stakeholder Engagement

98. What is the primary purpose of a project management information system (PMIS)?

Support project management activities
Track costs only
Create schedule only
Assign resources only

99. Which technique is used to resolve schedule conflicts?

Resource Smoothing
Pareto Analysis
Control Charts
Ishikawa Diagrams

100. What is the purpose of a project performance review?

Assess project progress
Initiate project
Identify risks
Estimate costs

101. Which process involves documenting project lessons learned?

Close Project or Phase
Monitor and Control Project Work
Direct and Manage Project Work
Develop Project Charter

102. What is the purpose of a project baseline?

Compare actual performance to planned
Track costs only
Create schedule only
Assign resources only

103. Which document defines how risks will be managed?

Risk Management Plan
Project Charter
WBS
Schedule

104. What is the primary purpose of a quality management plan?

Define quality standards and metrics
Track costs
Create schedule
Assign resources

105. Which technique is used to collect requirements from many stakeholders?

Questionnaires and Surveys
Interviews
Focus Groups
Brainstorming

106. What is the purpose of a project management plan?

Define how project will be executed
Track costs only
Create schedule only
Assign resources only

107. Which process involves identifying project stakeholders?

Identify Stakeholders
Plan Stakeholder Engagement
Manage Stakeholder Engagement
Monitor Stakeholder Engagement

108. What is the primary purpose of a communications management plan?

Define information distribution methods
Track costs
Create schedule
Assign resources

109. Which technique is used to estimate project durations?

Analogous Estimating
Pareto Analysis
Control Charts
Ishikawa Diagrams

110. What is the purpose of a project charter?

Authorize the project
Track costs
Create schedule
Assign resources

111. Which process involves defining project activities?

Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule

112. What is the purpose of a work breakdown structure (WBS)?

Decompose project deliverables
Track costs
Create schedule
Assign resources

113. Which document defines how scope will be managed?

Scope Management Plan
Project Charter
WBS
Schedule

114. What is the primary purpose of a stakeholder register?

Document stakeholder information
Track costs
Create schedule
Assign resources

115. Which technique is used to identify risks?

Checklist Analysis
Pareto Analysis
Control Charts
Ishikawa Diagrams

116. What is the purpose of a project schedule network diagram?

Show activity relationships
Track costs
Assign resources
Manage quality

117. Which process involves developing the project budget?

Determine Budget
Estimate Costs
Control Costs
Plan Cost Management

118. What is the primary purpose of a risk register?

Document identified risks
Track costs
Create schedule
Assign resources

119. Which technique is used to compress the project schedule?

Crashing
Pareto Analysis
Control Charts
Ishikawa Diagrams

120. What is the purpose of a change control system?

Manage changes to project baselines
Track costs
Create schedule
Assign resources

121. Which process involves verifying project deliverables?

Validate Scope
Control Quality
Manage Quality
Plan Quality Management

122. What is the purpose of a project management plan?

Define how project will be executed
Track costs only
Create schedule only
Assign resources only

123. Which document defines how resources will be managed?

Resource Management Plan
Project Charter
WBS
Schedule

124. What is the primary purpose of a communications matrix?

Define communication requirements
Track costs
Create schedule
Assign resources

125. Which technique is used to optimize resource allocation?

Resource Leveling
Pareto Analysis
Control Charts
Ishikawa Diagrams

126. What is the purpose of a work performance report?

Provide project status information
Initiate project
Identify risks
Estimate costs

127. Which process involves implementing approved changes?

Direct and Manage Project Work
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase

128. What is the primary purpose of a procurement statement of work?

Describe procurement items in detail
Track costs
Create schedule
Assign resources

129. Which technique is used to analyze project variances?

Variance Analysis
Pareto Analysis
Control Charts
Ishikawa Diagrams

130. What is the purpose of a project governance framework?

Define decision-making processes
Track costs
Create schedule
Assign resources

131. Which process involves verifying that deliverables meet requirements?

Control Quality
Manage Quality
Plan Quality Management
Validate Scope

132. What is the purpose of a responsibility assignment matrix (RAM)?

Define who does what work
Track costs
Create schedule
Manage quality

133. Which document defines how costs will be estimated and controlled?

Cost Management Plan
Project Charter
WBS
Risk Register

134. What is the primary purpose of a risk breakdown structure?

Categorize identified risks
Track costs
Create schedule
Assign resources

135. Which technique is used to analyze project performance?

Earned Value Management
Pareto Analysis
Control Charts
Ishikawa Diagrams

136. What is the purpose of a project scope statement?

Define project deliverables and work
Track costs
Create schedule
Assign resources

137. Which process involves monitoring stakeholder engagement?

Monitor Stakeholder Engagement
Identify Stakeholders
Plan Stakeholder Engagement
Manage Stakeholder Engagement

138. What is the primary purpose of a project management information system (PMIS)?

Support project management activities
Track costs only
Create schedule only
Assign resources only

139. Which technique is used to resolve schedule conflicts?

Resource Smoothing
Pareto Analysis
Control Charts
Ishikawa Diagrams

140. What is the purpose of a project performance review?

Assess project progress
Initiate project
Identify risks
Estimate costs

141. Which process involves documenting project lessons learned?

Close Project or Phase
Monitor and Control Project Work
Direct and Manage Project Work
Develop Project Charter

142. What is the purpose of a project baseline?

Compare actual performance to planned
Track costs only
Create schedule only
Assign resources only

143. Which document defines how risks will be managed?

Risk Management Plan
Project Charter
WBS
Schedule

144. What is the primary purpose of a quality management plan?

Define quality standards and metrics
Track costs
Create schedule
Assign resources

145. Which technique is used to collect requirements from many stakeholders?

Questionnaires and Surveys
Interviews
Focus Groups
Brainstorming

146. What is the purpose of a project management plan?

Define how project will be executed
Track costs only
Create schedule only
Assign resources only

147. Which process involves identifying project stakeholders?

Identify Stakeholders
Plan Stakeholder Engagement
Manage Stakeholder Engagement
Monitor Stakeholder Engagement

148. What is the primary purpose of a communications management plan?

Define information distribution methods
Track costs
Create schedule
Assign resources

149. Which technique is used to estimate project durations?

Analogous Estimating
Pareto Analysis
Control Charts
Ishikawa Diagrams

150. What is the purpose of a project charter?

Authorize the project
Track costs
Create schedule
Assign resources

151. Which process involves defining project activities?

Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule

152. What is the purpose of a work breakdown structure (WBS)?

Decompose project deliverables
Track costs
Create schedule
Assign resources

153. Which document defines how scope will be managed?

Scope Management Plan
Project Charter
WBS
Schedule

154. What is the primary purpose of a stakeholder register?

Document stakeholder information
Track costs
Create schedule
Assign resources

155. Which technique is used to identify risks?

Checklist Analysis
Pareto Analysis
Control Charts
Ishikawa Diagrams

156. What is the purpose of a project schedule network diagram?

Show activity relationships
Track costs
Assign resources
Manage quality

157. Which process involves developing the project budget?

Determine Budget
Estimate Costs
Control Costs
Plan Cost Management

158. What is the primary purpose of a risk register?

Document identified risks
Track costs
Create schedule
Assign resources

159. Which technique is used to compress the project schedule?

Crashing
Pareto Analysis
Control Charts
Ishikawa Diagrams

160. What is the purpose of a requirements traceability matrix?

To track requirements through the project lifecycle
To estimate costs
To schedule activities
To manage quality

The Pmi Ca0 001 Certified Associate In Project Management certification is a globally recognized credential for IT professionals. This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.