1. Which process is used to track project performance?
Monitor and Control Project Work
Develop Project Charter
Define Scope
Close Project or Phase
Show Answer
✅ Correct Answer: Monitor and Control Project Work
2. What document formally authorizes a project?
Project Charter
Project Scope Statement
Project Plan
Risk Register
Show Answer
✅ Correct Answer: Project Charter
3. Which knowledge area includes the process "Develop Project Management Plan"?
Project Integration Management
Project Scope Management
Project Schedule Management
Project Risk Management
Show Answer
✅ Correct Answer: Project Integration Management
4. Which project management plan defines how project changes will be handled?
Change Management Plan
Quality Management Plan
Risk Management Plan
Stakeholder Engagement Plan
Show Answer
✅ Correct Answer: Change Management Plan
5. What technique is used to determine the cause of a problem in project management?
Root Cause Analysis
Delphi Technique
Monte Carlo Simulation
Earned Value Management
Show Answer
✅ Correct Answer: Root Cause Analysis
6. Which process ensures that all work required for the project is completed?
Validate Scope
Develop Schedule
Perform Integrated Change Control
Control Risks
Show Answer
✅ Correct Answer: Validate Scope
7. Which document defines project roles and responsibilities?
Responsibility Assignment Matrix (RAM)
Project Charter
Project Scope Statement
Risk Register
Show Answer
✅ Correct Answer: Responsibility Assignment Matrix (RAM)
8. What is a Work Breakdown Structure (WBS) used for?
Breaking down project deliverables
Developing risk response strategies
Defining quality metrics
Estimating project costs
Show Answer
✅ Correct Answer: Breaking down project deliverables
9. Which process is used to manage project risks proactively?
Plan Risk Responses
Monitor and Control Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Show Answer
✅ Correct Answer: Plan Risk Responses
10. Which tool is commonly used for project scheduling?
Gantt Chart
Pareto Chart
Ishikawa Diagram
Scatter Diagram
Show Answer
✅ Correct Answer: Gantt Chart
11. Which project management methodology emphasizes flexibility and iterative progress?
Agile
Waterfall
Critical Path Method
Six Sigma
Show Answer
✅ Correct Answer: Agile
12. Which of the following is a key stakeholder in a project?
Sponsor
Competitor
Regulator
Marketing Manager
Show Answer
✅ Correct Answer: Sponsor
13. What is the primary goal of stakeholder management?
Ensuring stakeholder engagement
Minimizing project costs
Increasing project duration
Avoiding risk management
Show Answer
✅ Correct Answer: Ensuring stakeholder engagement
14. Which document helps to track changes in a project?
Change Log
Risk Register
Lessons Learned Document
Stakeholder Register
Show Answer
✅ Correct Answer: Change Log
15. Which process ensures that project deliverables meet quality standards?
Control Quality
Develop Project Charter
Define Scope
Plan Communications Management
Show Answer
✅ Correct Answer: Control Quality
16. What is the primary purpose of Earned Value Management (EVM)?
Measuring project performance
Identifying project stakeholders
Developing project risks
Assigning project roles
Show Answer
✅ Correct Answer: Measuring project performance
17. Which of the following is an output of the "Close Project or Phase" process?
Final Report
Risk Register
Quality Metrics
Scope Baseline
Show Answer
✅ Correct Answer: Final Report
18. Which type of contract places the most financial risk on the seller?
Firm-Fixed-Price (FFP)
Cost-Plus-Incentive-Fee (CPIF)
Time and Material (T&M)
Cost-Plus-Fixed-Fee (CPFF)
Show Answer
✅ Correct Answer: Firm-Fixed-Price (FFP)
19. What is the primary goal of cost management in a project?
Ensuring the project is completed within the approved budget
Minimizing stakeholder engagement
Avoiding risk management
Maximizing project duration
Show Answer
✅ Correct Answer: Ensuring the project is completed within the approved budget
20. Which project document includes information about project assumptions and constraints?
Project Scope Statement
Risk Register
Resource Management Plan
Quality Management Plan
Show Answer
✅ Correct Answer: Project Scope Statement
21. Which communication method is best for resolving complex project conflicts?
Face-to-face meetings
Emails
Instant messaging
Status reports
Show Answer
✅ Correct Answer: Face-to-face meetings
22. Which process group includes the most processes?
Planning
Initiating
Executing
Monitoring and Controlling
Show Answer
✅ Correct Answer: Planning
23. What is the primary purpose of a project charter?
Authorize the project
Define detailed scope
Create WBS
Develop schedule
Show Answer
✅ Correct Answer: Authorize the project
24. Which technique is used to identify all project stakeholders?
Stakeholder analysis
SWOT analysis
PERT analysis
Earned value analysis
Show Answer
✅ Correct Answer: Stakeholder analysis
25. What is the key output of the Define Scope process?
Project scope statement
WBS
Schedule baseline
Risk register
Show Answer
✅ Correct Answer: Project scope statement
26. Which document contains the approved project budget?
Cost baseline
Project charter
Risk register
Stakeholder register
Show Answer
✅ Correct Answer: Cost baseline
27. What is the purpose of a quality management plan?
Define quality standards
Authorize the project
Identify risks
Assign resources
Show Answer
✅ Correct Answer: Define quality standards
28. Which process creates the work breakdown structure (WBS)?
Create WBS
Define scope
Develop schedule
Plan scope management
Show Answer
✅ Correct Answer: Create WBS
29. What is the main purpose of a responsibility assignment matrix (RAM)?
Define roles and responsibilities
Track project costs
Manage risks
Control quality
Show Answer
✅ Correct Answer: Define roles and responsibilities
30. Which technique is used to estimate activity durations?
Three-point estimating
Earned value management
Critical path method
Monte Carlo simulation
Show Answer
✅ Correct Answer: Three-point estimating
31. What is the purpose of a communications management plan?
Define information distribution methods
Authorize the project
Create WBS
Develop schedule
Show Answer
✅ Correct Answer: Define information distribution methods
32. Which process identifies potential project risks?
Identify Risks
Plan Risk Responses
Perform Qualitative Risk Analysis
Monitor Risks
Show Answer
✅ Correct Answer: Identify Risks
33. What is the key benefit of the Perform Integrated Change Control process?
Maintain baseline integrity
Identify stakeholders
Create WBS
Develop team
Show Answer
✅ Correct Answer: Maintain baseline integrity
34. Which document tracks identified project risks?
Risk register
Project charter
WBS
Stakeholder register
Show Answer
✅ Correct Answer: Risk register
35. What is the purpose of a stakeholder engagement plan?
Manage stakeholder expectations
Define project scope
Create WBS
Develop schedule
Show Answer
✅ Correct Answer: Manage stakeholder expectations
36. Which technique is used to compress a project schedule?
Crashing
Resource leveling
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Crashing
37. What is the primary output of the Acquire Resources process?
Physical resource assignments
Project charter
WBS
Risk register
Show Answer
✅ Correct Answer: Physical resource assignments
38. Which process ensures project deliverables meet requirements?
Control Quality
Plan Quality Management
Manage Quality
Validate Scope
Show Answer
✅ Correct Answer: Control Quality
39. What is the purpose of a lessons learned register?
Document project knowledge
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Document project knowledge
40. Which technique is used to analyze project risks numerically?
Monte Carlo simulation
SWOT analysis
Delphi technique
Root cause analysis
Show Answer
✅ Correct Answer: Monte Carlo simulation
41. What is the key output of the Develop Team process?
Team performance assessments
Project charter
WBS
Risk register
Show Answer
✅ Correct Answer: Team performance assessments
42. Which process ensures deliverables are formally accepted?
Validate Scope
Control Quality
Close Project or Phase
Monitor and Control Project Work
Show Answer
✅ Correct Answer: Validate Scope
43. What is the purpose of a procurement management plan?
Define procurement approach
Authorize the project
Create WBS
Develop schedule
Show Answer
✅ Correct Answer: Define procurement approach
44. Which technique is used to identify quality requirements?
Cost-benefit analysis
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Cost-benefit analysis
45. What is the primary output of the Plan Risk Management process?
Risk management plan
Risk register
Project charter
WBS
Show Answer
✅ Correct Answer: Risk management plan
46. Which process involves obtaining seller responses?
Conduct Procurements
Plan Procurement Management
Control Procurements
Close Procurements
Show Answer
✅ Correct Answer: Conduct Procurements
47. What is the purpose of a milestone list?
Identify significant schedule points
Authorize the project
Define scope
Develop team
Show Answer
✅ Correct Answer: Identify significant schedule points
48. Which technique is used to resolve conflicts?
Collaboration
Avoidance
Compromise
Smoothing
Show Answer
✅ Correct Answer: Collaboration
49. What is the key output of the Identify Stakeholders process?
Stakeholder register
Project charter
WBS
Risk register
Show Answer
✅ Correct Answer: Stakeholder register
50. Which process involves implementing risk responses?
Implement Risk Responses
Plan Risk Responses
Monitor Risks
Identify Risks
Show Answer
✅ Correct Answer: Implement Risk Responses
51. What is the purpose of a project management plan?
Define how project will be executed
Authorize the project
Create WBS
Develop team
Show Answer
✅ Correct Answer: Define how project will be executed
52. Which technique is used to analyze project variances?
Earned value management
Critical path method
Monte Carlo simulation
Three-point estimating
Show Answer
✅ Correct Answer: Earned value management
53. What is the primary output of the Estimate Costs process?
Cost estimates
Cost baseline
Project charter
WBS
Show Answer
✅ Correct Answer: Cost estimates
54. Which process involves tracking team member performance?
Manage Team
Develop Team
Plan Resource Management
Acquire Resources
Show Answer
✅ Correct Answer: Manage Team
55. What is the purpose of a change control system?
Manage project changes
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Manage project changes
56. Which technique is used to sequence project activities?
Precedence diagramming method
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Precedence diagramming method
57. What is the key output of the Plan Schedule Management process?
Schedule management plan
Project schedule
Project charter
WBS
Show Answer
✅ Correct Answer: Schedule management plan
58. Which process involves distributing project information?
Manage Communications
Plan Communications Management
Monitor Communications
Identify Stakeholders
Show Answer
✅ Correct Answer: Manage Communications
59. What is the purpose of a risk breakdown structure (RBS)?
Categorize project risks
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Categorize project risks
60. Which technique is used to evaluate project alternatives?
Decision tree analysis
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Decision tree analysis
61. What is the primary output of the Estimate Activity Durations process?
Duration estimates
Project schedule
Project charter
WBS
Show Answer
✅ Correct Answer: Duration estimates
62. Which process involves improving team competencies?
Develop Team
Manage Team
Plan Resource Management
Acquire Resources
Show Answer
✅ Correct Answer: Develop Team
63. What is the purpose of a quality control measurement?
Verify deliverables meet requirements
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Verify deliverables meet requirements
64. Which technique is used to analyze project performance?
Trend analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Trend analysis
65. What is the key output of the Plan Procurement Management process?
Procurement management plan
Procurement documents
Project charter
WBS
Show Answer
✅ Correct Answer: Procurement management plan
66. Which process involves finalizing all project activities?
Close Project or Phase
Monitor and Control Project Work
Direct and Manage Project Work
Perform Integrated Change Control
Show Answer
✅ Correct Answer: Close Project or Phase
67. What is the purpose of a requirements traceability matrix?
Track requirements throughout project
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Track requirements throughout project
68. Which technique is used to identify project constraints?
Assumptions and constraints analysis
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Assumptions and constraints analysis
69. What is the primary output of the Define Activities process?
Activity list
Project schedule
Project charter
WBS
Show Answer
✅ Correct Answer: Activity list
70. Which process involves resolving procurement issues?
Control Procurements
Plan Procurement Management
Conduct Procurements
Close Procurements
Show Answer
✅ Correct Answer: Control Procurements
71. What is the purpose of a resource breakdown structure?
Categorize project resources
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Categorize project resources
72. Which technique is used to evaluate project performance?
Earned value analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Earned value analysis
73. What is the key output of the Plan Stakeholder Engagement process?
Stakeholder engagement plan
Stakeholder register
Project charter
WBS
Show Answer
✅ Correct Answer: Stakeholder engagement plan
74. Which process involves implementing approved changes?
Direct and Manage Project Work
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
Show Answer
✅ Correct Answer: Direct and Manage Project Work
75. What is the purpose of a schedule baseline?
Track schedule performance
Authorize the project
Define scope
Develop team
Show Answer
✅ Correct Answer: Track schedule performance
76. Which technique is used to collect requirements?
Interviews
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Interviews
77. What is the primary output of the Estimate Activity Resources process?
Resource requirements
Resource breakdown structure
Project charter
WBS
Show Answer
✅ Correct Answer: Resource requirements
78. Which process involves managing stakeholder expectations?
Manage Stakeholder Engagement
Plan Stakeholder Engagement
Monitor Stakeholder Engagement
Identify Stakeholders
Show Answer
✅ Correct Answer: Manage Stakeholder Engagement
79. What is the purpose of a cost baseline?
Track project costs
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Track project costs
80. Which technique is used to analyze project quality?
Control charts
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Control charts
81. What is the key output of the Plan Quality Management process?
Quality management plan
Quality metrics
Project charter
WBS
Show Answer
✅ Correct Answer: Quality management plan
82. Which process involves finalizing procurement contracts?
Close Procurements
Plan Procurement Management
Conduct Procurements
Control Procurements
Show Answer
✅ Correct Answer: Close Procurements
83. What is the purpose of a scope baseline?
Track scope performance
Authorize the project
Define team roles
Develop schedule
Show Answer
✅ Correct Answer: Track scope performance
84. Which technique is used to develop the project schedule?
Critical path method
Earned value management
Monte Carlo simulation
Three-point estimating
Show Answer
✅ Correct Answer: Critical path method
85. What is the primary output of the Sequence Activities process?
Project schedule network diagram
Project schedule
Project charter
WBS
Show Answer
✅ Correct Answer: Project schedule network diagram
86. Which process involves improving project processes?
Manage Quality
Plan Quality Management
Control Quality
Validate Scope
Show Answer
✅ Correct Answer: Manage Quality
87. What is the purpose of a risk response plan?
Address identified risks
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Address identified risks
88. Which technique is used to evaluate project feasibility?
Cost-benefit analysis
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Cost-benefit analysis
89. What is the key output of the Develop Schedule process?
Project schedule
Schedule baseline
Project charter
WBS
Show Answer
✅ Correct Answer: Project schedule
90. Which process involves monitoring stakeholder relationships?
Monitor Stakeholder Engagement
Plan Stakeholder Engagement
Manage Stakeholder Engagement
Identify Stakeholders
Show Answer
✅ Correct Answer: Monitor Stakeholder Engagement
91. What is the purpose of a communications matrix?
Define communication requirements
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Define communication requirements
92. Which technique is used to analyze project scope?
Product analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Product analysis
93. What is the primary output of the Determine Budget process?
Cost baseline
Cost estimates
Project charter
WBS
Show Answer
✅ Correct Answer: Cost baseline
94. Which process involves verifying project deliverables?
Validate Scope
Control Quality
Close Project or Phase
Monitor and Control Project Work
Show Answer
✅ Correct Answer: Validate Scope
95. What is the purpose of a risk audit?
Evaluate risk process effectiveness
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Evaluate risk process effectiveness
96. Which technique is used to estimate project costs?
Analogous estimating
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Analogous estimating
97. What is the key output of the Plan Resource Management process?
Resource management plan
Team charter
Project charter
WBS
Show Answer
✅ Correct Answer: Resource management plan
98. Which process involves improving team skills?
Develop Team
Manage Team
Plan Resource Management
Acquire Resources
Show Answer
✅ Correct Answer: Develop Team
99. What is the purpose of a quality audit?
Evaluate quality process effectiveness
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Evaluate quality process effectiveness
100. Which technique is used to analyze project risks qualitatively?
Probability and impact matrix
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Probability and impact matrix
101. What is the primary output of the Acquire Resources process?
Resource calendars
Physical resource assignments
Project charter
WBS
Show Answer
✅ Correct Answer: Resource calendars
102. Which process involves managing procurement relationships?
Control Procurements
Plan Procurement Management
Conduct Procurements
Close Procurements
Show Answer
✅ Correct Answer: Control Procurements
103. What is the purpose of a stakeholder analysis?
Identify stakeholder interests
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Identify stakeholder interests
104. Which technique is used to develop project estimates?
Bottom-up estimating
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Bottom-up estimating
105. What is the key output of the Plan Communications Management process?
Communications management plan
Stakeholder engagement plan
Project charter
WBS
Show Answer
✅ Correct Answer: Communications management plan
106. Which process involves implementing quality standards?
Manage Quality
Plan Quality Management
Control Quality
Validate Scope
Show Answer
✅ Correct Answer: Manage Quality
107. What is the purpose of a risk register?
Document identified risks
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Document identified risks
108. Which technique is used to evaluate project alternatives?
Multi-criteria decision analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Multi-criteria decision analysis
109. What is the primary output of the Develop Project Charter process?
Project charter
Project management plan
WBS
Risk register
Show Answer
✅ Correct Answer: Project charter
110. Which process involves monitoring project work?
Monitor and Control Project Work
Direct and Manage Project Work
Perform Integrated Change Control
Close Project or Phase
Show Answer
✅ Correct Answer: Monitor and Control Project Work
111. What is the purpose of a project scope statement?
Define project deliverables
Authorize the project
Assign resources
Develop schedule
Show Answer
✅ Correct Answer: Define project deliverables
112. Which technique is used to analyze project performance?
Variance analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Variance analysis
113. What is the key output of the Plan Risk Responses process?
Risk response plans
Risk register updates
Project charter
WBS
Show Answer
✅ Correct Answer: Risk response plans
114. Which process involves managing project changes?
Perform Integrated Change Control
Monitor and Control Project Work
Direct and Manage Project Work
Close Project or Phase
Show Answer
✅ Correct Answer: Perform Integrated Change Control
115. What is the purpose of a work performance report?
Communicate project status
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Communicate project status
116. Which technique is used to collect project requirements?
Focus groups
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Focus groups
117. What is the primary output of the Estimate Activity Resources process?
Resource breakdown structure
Resource requirements
Project charter
WBS
Show Answer
✅ Correct Answer: Resource breakdown structure
118. Which process involves improving team performance?
Develop Team
Manage Team
Plan Resource Management
Acquire Resources
Show Answer
✅ Correct Answer: Develop Team
119. What is the purpose of a procurement statement of work?
Define procurement requirements
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Define procurement requirements
120. Which technique is used to analyze project quality?
Flowcharts
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Flowcharts
121. What is the key output of the Plan Stakeholder Engagement process?
Stakeholder engagement assessment matrix
Stakeholder engagement plan
Project charter
WBS
Show Answer
✅ Correct Answer: Stakeholder engagement assessment matrix
122. Which process involves managing project communications?
Manage Communications
Plan Communications Management
Monitor Communications
Identify Stakeholders
Show Answer
✅ Correct Answer: Manage Communications
123. What is the purpose of a project management information system (PMIS)?
Support project management processes
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Support project management processes
124. Which technique is used to develop project schedules?
Critical chain method
Earned value management
Monte Carlo simulation
Three-point estimating
Show Answer
✅ Correct Answer: Critical chain method
125. What is the primary output of the Define Scope process?
Project scope statement
WBS
Scope baseline
Project charter
Show Answer
✅ Correct Answer: Project scope statement
126. Which process involves managing project team conflicts?
Manage Team
Develop Team
Plan Resource Management
Acquire Resources
Show Answer
✅ Correct Answer: Manage Team
127. What is the purpose of a risk management plan?
Define risk management approach
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Define risk management approach
128. Which technique is used to evaluate project performance?
Earned value analysis
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Earned value analysis
129. What is the key output of the Develop Project Management Plan process?
Project management plan
Project charter
WBS
Risk register
Show Answer
✅ Correct Answer: Project management plan
130. Which process involves finalizing all project procurements?
Close Procurements
Plan Procurement Management
Conduct Procurements
Control Procurements
Show Answer
✅ Correct Answer: Close Procurements
131. What is the purpose of a requirements documentation?
Document stakeholder needs
Authorize the project
Define team roles
Develop schedule
Show Answer
✅ Correct Answer: Document stakeholder needs
132. Which technique is used to analyze project risks?
SWOT analysis
Critical path method
Earned value management
Three-point estimating
Show Answer
✅ Correct Answer: SWOT analysis
133. What is the primary output of the Plan Scope Management process?
Scope management plan
Project scope statement
WBS
Project charter
Show Answer
✅ Correct Answer: Scope management plan
134. Which process involves managing project quality?
Manage Quality
Plan Quality Management
Control Quality
Validate Scope
Show Answer
✅ Correct Answer: Manage Quality
135. What is the purpose of a stakeholder register?
Document stakeholder information
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Document stakeholder information
136. Which technique is used to estimate project durations?
Analogous estimating
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Analogous estimating
137. What is the key output of the Plan Cost Management process?
Cost management plan
Cost baseline
Project charter
WBS
Show Answer
✅ Correct Answer: Cost management plan
138. Which process involves managing project resources?
Control Resources
Plan Resource Management
Acquire Resources
Develop Team
Show Answer
✅ Correct Answer: Control Resources
139. What is the purpose of a change log?
Track project changes
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Track project changes
140. Which technique is used to analyze project quality?
Pareto charts
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Pareto charts
141. What is the primary output of the Identify Risks process?
Risk register
Risk management plan
Project charter
WBS
Show Answer
✅ Correct Answer: Risk register
142. Which process involves managing project communications?
Monitor Communications
Plan Communications Management
Manage Communications
Identify Stakeholders
Show Answer
✅ Correct Answer: Monitor Communications
143. What is the purpose of a lessons learned register?
Document project knowledge
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Document project knowledge
144. Which technique is used to develop project budgets?
Cost aggregation
Critical path method
Earned value management
Monte Carlo simulation
Show Answer
✅ Correct Answer: Cost aggregation
145. What is the key output of the Plan Schedule Management process?
Schedule management plan
Project schedule
Project charter
WBS
Show Answer
✅ Correct Answer: Schedule management plan
146. Which process involves managing stakeholder expectations?
Monitor Stakeholder Engagement
Plan Stakeholder Engagement
Manage Stakeholder Engagement
Identify Stakeholders
Show Answer
✅ Correct Answer: Monitor Stakeholder Engagement
147. What is the purpose of a quality metrics?
Measure quality performance
Authorize the project
Define scope
Develop schedule
Show Answer
✅ Correct Answer: Measure quality performance
148. Which technique is used to analyze project risks?
Influence diagrams
Critical path method
Three-point estimating
Monte Carlo simulation
Show Answer
✅ Correct Answer: Influence diagrams
149. What is the primary output of the Develop Team process?
Team performance assessments
Resource calendars
Project charter
WBS
Show Answer
✅ Correct Answer: Team performance assessments
150. Which process involves finalizing all project activities?
Close Project or Phase
Monitor and Control Project Work
Direct and Manage Project Work
Perform Integrated Change Control
Show Answer
✅ Correct Answer: Close Project or Phase
151. What is the purpose of a project management plan?
Define how project will be executed
Authorize the project
Create WBS
Develop team
Show Answer
✅ Correct Answer: Define how project will be executed