✅ Correct Answer: To facilitate Scrum events and remove obstacles
2. Who can modify the product backlog?
Scrum Master
Product Owner
Development Team
Stakeholders
✅ Correct Answer: Product Owner
3. Which of the following is NOT a Scrum event?
Sprint Planning
Sprint Review
Daily Standup
Task estimation
✅ Correct Answer: Task estimation
4. How long is a typical Scrum sprint?
1 to 4 weeks
2 to 3 weeks
4 to 6 weeks
8 weeks
✅ Correct Answer: 1 to 4 weeks
5. What is the role of the Scrum Master during a sprint retrospective?
To facilitate discussions and ensure continuous improvement
To give a report on team progress
To create the product backlog
To assign tasks to team members
✅ Correct Answer: To facilitate discussions and ensure continuous improvement
6. What is the main responsibility of the Development Team in Scrum?
To deliver a potentially shippable product increment
To manage the product backlog
To facilitate Scrum events
To monitor team performance
✅ Correct Answer: To deliver a potentially shippable product increment
7. Who is responsible for defining the sprint goal?
Scrum Master
Product Owner
Development Team and Product Owner collaboratively
Stakeholders
✅ Correct Answer: Development Team and Product Owner collaboratively
8. What should happen if a team member consistently underperforms?
The Scrum Master should remove them from the team
The team should discuss it and try to resolve the issue collectively
The Product Owner should assign fewer tasks to them
The manager should step in to manage the individual
✅ Correct Answer: The team should discuss it and try to resolve the issue collectively
9. What does a Scrum Master do if external stakeholders disrupt the Development Team during a sprint?
Allow stakeholders to make changes if necessary
Shield the team from interruptions and remind stakeholders about Scrum practices
Pause the sprint to accommodate the changes
Ask the Product Owner to handle external requests
✅ Correct Answer: Shield the team from interruptions and remind stakeholders about Scrum practices
10. What is the most important characteristic of a Scrum team?
Hierarchical structure
Cross-functionality and self-organization
Strict division of roles and responsibilities
Following a command-and-control approach
✅ Correct Answer: Cross-functionality and self-organization
11. Which artifact provides transparency into the work planned for a sprint?
Product Backlog
Sprint Backlog
Burndown Chart
Increment
✅ Correct Answer: Sprint Backlog
12. What should happen during the Daily Scrum?
Team members report to the Scrum Master
The team discusses progress and potential obstacles
The Product Owner assigns new tasks
The team reviews sprint planning documents
✅ Correct Answer: The team discusses progress and potential obstacles
13. Which of the following is NOT a role in Scrum?
Scrum Master
Product Owner
Project Manager
Development Team
✅ Correct Answer: Project Manager
14. How does a Scrum Master serve the Development Team?
By assigning tasks to the team
By ensuring adherence to Scrum principles and removing impediments
By managing project deadlines
By making technical decisions for the team
✅ Correct Answer: By ensuring adherence to Scrum principles and removing impediments
15. What is the purpose of a Sprint Retrospective?
To review progress with stakeholders
To inspect and improve team processes
To demonstrate completed work
To update the product backlog
✅ Correct Answer: To inspect and improve team processes
16. Which of the following is NOT an official Scrum event?
Sprint Planning
Sprint Review
Daily Standup
Sprint Execution
✅ Correct Answer: Sprint Execution
17. What happens if work is not completed in a sprint?
The work goes back to the product backlog for re-prioritization
The work is carried over to the next sprint automatically
The Scrum Master assigns it to a team member
The Product Owner must complete it
✅ Correct Answer: The work goes back to the product backlog for re-prioritization
18. How does a Scrum Team determine the duration of a Sprint?
Based on team consensus and the nature of work
Determined by management
Always set to 2 weeks
Decided by the Scrum Master
✅ Correct Answer: Based on team consensus and the nature of work
19. Who owns the Definition of Done?
Scrum Master
Product Owner
Development Team
Stakeholders
✅ Correct Answer: Development Team
20. When can a Development Team change the Sprint Backlog?
Only before the sprint starts
During the sprint, as more is learned
Never, it must be fixed at Sprint Planning
Only if approved by management
✅ Correct Answer: During the sprint, as more is learned
The Psm I certification is a globally recognized credential for IT professionals.
This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.
Want more practice? Check out our other mock exams: