39. What is the recommended approach when multiple teams work on the same product?
Use one Product Backlog for the product
Each team maintains its own Product Backlog
Combine all work into one Sprint
Appoint a lead Product Owner
✅ Correct Answer: Use one Product Backlog for the product
40. What is the purpose of timeboxing in Scrum?
To create regularity and limit risk
To ensure all work is completed
To measure team productivity
To satisfy stakeholders
✅ Correct Answer: To create regularity and limit risk
41. Who is responsible for tracking Sprint progress?
The entire Scrum Team
The Scrum Master
The Product Owner
The Development Team Lead
✅ Correct Answer: The entire Scrum Team
42. What should the Development Team do if it realizes it won't complete all Sprint Backlog items?
Collaborate with the Product Owner to adjust scope
Work overtime to complete everything
Extend the Sprint duration
Move unfinished items to the next Sprint
✅ Correct Answer: Collaborate with the Product Owner to adjust scope
43. Which of these is NOT a Scrum Event?
Backlog Refinement
Sprint Planning
Daily Scrum
Sprint Retrospective
✅ Correct Answer: Backlog Refinement
44. What is the Scrum Master's role in Sprint Planning?
Facilitating the meeting
Deciding what work gets done
Estimating tasks
Writing user stories
✅ Correct Answer: Facilitating the meeting
45. How should a Scrum Team handle technical debt?
Include it in the Definition of Done
Address it in a separate Sprint
Ignore it to maintain velocity
Assign it to specialists
✅ Correct Answer: Include it in the Definition of Done
46. What is the primary purpose of the Sprint Burndown Chart?
To track progress toward completing Sprint work
To measure team productivity
To report to management
To estimate future Sprints
✅ Correct Answer: To track progress toward completing Sprint work
47. Who decides how to turn Product Backlog items into Increments?
The Development Team
The Product Owner
The Scrum Master
The stakeholders
✅ Correct Answer: The Development Team
48. What is the Scrum Master's responsibility regarding Scrum?
Ensuring Scrum is understood and enacted
Managing the Development Team's work
Setting the Sprint Goal
Prioritizing the Product Backlog
✅ Correct Answer: Ensuring Scrum is understood and enacted
49. When should the Product Backlog be prioritized?
Continuously as needed
Only during Sprint Planning
At the start of each release
During the Sprint Review
✅ Correct Answer: Continuously as needed
50. What is the main benefit of short Sprints?
More frequent feedback and adaptation
Less planning overhead
Higher velocity
More work completed
✅ Correct Answer: More frequent feedback and adaptation
51. Who should participate in Product Backlog refinement?
The Scrum Team and stakeholders
Only the Product Owner
Only the Development Team
Only the Scrum Master and Product Owner
✅ Correct Answer: The Scrum Team and stakeholders
52. What is the Scrum Master's role in the Daily Scrum?
To ensure the meeting happens and stays within timebox
To lead the discussion
To take notes
To assign tasks
✅ Correct Answer: To ensure the meeting happens and stays within timebox
53. How often should the Definition of Done be updated?
As the team's capabilities improve
Never - it should remain constant
At the start of each project
Only when major problems occur
✅ Correct Answer: As the team's capabilities improve
54. What is the primary purpose of the Sprint Planning meeting?
To define what can be delivered and how
To assign all tasks to team members
To review stakeholder requirements
To estimate the entire Product Backlog
✅ Correct Answer: To define what can be delivered and how
55. Who creates the Sprint Backlog?
The Development Team
The Product Owner
The Scrum Master
The entire Scrum Team
✅ Correct Answer: The Development Team
56. What is the Scrum Master's responsibility regarding impediments?
To help remove impediments that are beyond the team's control
To solve all technical problems
To document all issues
To assign someone to fix every problem
✅ Correct Answer: To help remove impediments that are beyond the team's control
57. What is the recommended approach for scaling Scrum?
Nexus
Combine multiple teams into one large team
Have one Product Owner manage all teams
Create a hierarchy of Scrum Masters
✅ Correct Answer: Nexus
58. Who decides how to organize the Development Team's work?
The Development Team itself
The Scrum Master
The Product Owner
The most senior developer
✅ Correct Answer: The Development Team itself
59. What is the Scrum Master's role in the Sprint Retrospective?
Facilitating the meeting and ensuring Scrum values are followed
Leading the discussion
Documenting action items
Reporting on team performance
✅ Correct Answer: Facilitating the meeting and ensuring Scrum values are followed
60. What is the recommended approach for dealing with changing requirements?
Welcome changing requirements, even late in development
Freeze requirements after Sprint Planning
Only allow changes between Sprints
Create change control procedures
✅ Correct Answer: Welcome changing requirements, even late in development
The Pspo I certification is a globally recognized credential for IT professionals.
This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.
Want more practice? Check out our other mock exams: