✅ Correct Answer: Delegated decision-making within tolerances
36. Which process ensures product acceptance?
Closing a Project
Managing Product Delivery
Initiating a Project
Directing a Project
✅ Correct Answer: Closing a Project
37. What is the "Lessons Log"?
A repository for project lessons
A financial tracker
A risk assessment tool
A team schedule
✅ Correct Answer: A repository for project lessons
38. Who approves tolerances?
Project Board
Project Manager
Team Manager
Senior Supplier
✅ Correct Answer: Project Board
39. What is the output of "Starting Up a Project"?
Project Brief
Business Case
Work Package
Risk Register
✅ Correct Answer: Project Brief
40. Which principle emphasizes role clarity?
Defined Roles and Responsibilities
Focus on Products
Manage by Exception
Tailor to Suit the Project
✅ Correct Answer: Defined Roles and Responsibilities
41. What is the "Daily Log"?
An informal issue/action tracker
A formal change request log
A quality approval record
A stage boundary report
✅ Correct Answer: An informal issue/action tracker
42. Which theme monitors progress?
Progress
Risk
Organization
Business Case
✅ Correct Answer: Progress
43. Who creates the Project Plan?
Project Manager
Executive
Senior User
Team Manager
✅ Correct Answer: Project Manager
44. What defines risk management strategy?
Risk Management Approach
Quality Register
Issue Register
Work Package
✅ Correct Answer: Risk Management Approach
45. What is the "End Project Report"?
A summary of project performance
A stage authorization document
A daily task list
A stakeholder register
✅ Correct Answer: A summary of project performance
46. Which principle ensures product clarity?
Focus on Products
Learn from Experience
Manage by Stages
Continued Business Justification
✅ Correct Answer: Focus on Products
47. What is a "Checkpoint Report"?
A team-level progress update
A Business Case approval
A risk assessment
A project closure document
✅ Correct Answer: A team-level progress update
48. Who ensures supplier resource availability?
Senior Supplier
Executive
Project Manager
Senior User
✅ Correct Answer: Senior Supplier
49. What is the "Communication Management Approach"?
A stakeholder engagement strategy
A risk tracker
A work authorization document
A financial budget
✅ Correct Answer: A stakeholder engagement strategy
50. Which process authorizes project closure?
Closing a Project
Managing a Stage Boundary
Directing a Project
Initiating a Project
✅ Correct Answer: Closing a Project
51. What is a "Highlight Report"?
A stage progress update for the Project Board
A team task list
A risk assessment
A quality inspection record
✅ Correct Answer: A stage progress update for the Project Board
52. What defines quality expectations?
Quality Management Approach
Risk Register
Project Brief
Daily Log
✅ Correct Answer: Quality Management Approach
53. When is an "Exception Report" used?
When tolerances are forecast to be exceeded
For daily team updates
To approve work packages
During project startup
✅ Correct Answer: When tolerances are forecast to be exceeded
54. Which principle ensures lesson application?
Learn from Experience
Manage by Stages
Focus on Products
Defined Roles and Responsibilities
✅ Correct Answer: Learn from Experience
55. Who approves stage plans?
Project Board
Project Manager
Team Manager
Senior User
✅ Correct Answer: Project Board
56. What is a "Configuration Item Record"?
A product version/status tracker
A stakeholder role definition
A financial log
A risk assessment template
✅ Correct Answer: A product version/status tracker
57. Which theme defines roles?
Organization
Risk
Quality
Change
✅ Correct Answer: Organization
58. What is a "Product Status Account"?
A snapshot of product delivery status
A financial report
A risk assessment
A team review
✅ Correct Answer: A snapshot of product delivery status
59. What defines change control procedures?
Change Control Approach
Risk Register
Quality Register
Daily Log
✅ Correct Answer: Change Control Approach
60. What is the "Benefits Review Plan"?
A post-project benefits measurement strategy
A daily task tracker
A work authorization document
A team chart
✅ Correct Answer: A post-project benefits measurement strategy
61. Which PRINCE2 principle ensures that lessons from previous projects are applied?
Learn from Experience
Manage by Stages
Focus on Products
Continued Business Justification
✅ Correct Answer: Learn from Experience
62. What is the purpose of the "Project Product Description"?
To define the main deliverable’s scope and quality criteria
To track daily progress
To authorize work packages
To replace the Business Case
✅ Correct Answer: To define the main deliverable’s scope and quality criteria
63. Which role ensures that supplier deliverables meet technical requirements?
Senior Supplier
Executive
Project Manager
Senior User
✅ Correct Answer: Senior Supplier
64. What is the "Product Status Account"?
A report on the status of all project products
A financial summary
A risk assessment document
A team performance review
✅ Correct Answer: A report on the status of all project products
65. Which PRINCE2 principle allows for flexibility in project management?
Tailor to Suit the Project
Defined Roles and Responsibilities
Manage by Exception
Focus on Products
✅ Correct Answer: Tailor to Suit the Project
66. What is the purpose of the "Exception Plan"?
To recover from a stage that has exceeded tolerances
To replace the Project Plan
To authorize the next stage
To document stakeholder feedback
✅ Correct Answer: To recover from a stage that has exceeded tolerances
67. Which document defines the project’s approach to communication?
Communication Management Approach
Risk Register
Issue Register
Daily Log
✅ Correct Answer: Communication Management Approach
68. What is the role of the "Team Manager"?
To deliver work packages within constraints
To approve the Business Case
To define project tolerances
To oversee project closure
✅ Correct Answer: To deliver work packages within constraints
69. Which PRINCE2 theme ensures that products meet defined quality criteria?
Quality
Risk
Change
Progress
✅ Correct Answer: Quality
70. What is the purpose of the "End Stage Report"?
To summarize stage performance and request approval for the next stage
To track daily issues
To define work packages
To replace the Project Plan
✅ Correct Answer: To summarize stage performance and request approval for the next stage
71. Which PRINCE2 process ensures that work packages are delivered?
Managing Product Delivery
Controlling a Stage
Initiating a Project
Directing a Project
✅ Correct Answer: Managing Product Delivery
72. What is the purpose of the "Configuration Management Approach"?
To track product versions and changes
To define stakeholder roles
To manage risks
To authorize work packages
✅ Correct Answer: To track product versions and changes
73. Which PRINCE2 principle ensures that projects are divided into manageable stages?
Manage by Stages
Focus on Products
Continued Business Justification
Defined Roles and Responsibilities
✅ Correct Answer: Manage by Stages
74. What is the purpose of the "Lessons Report"?
To document lessons for future projects
To track daily progress
To define work packages
To authorize changes
✅ Correct Answer: To document lessons for future projects
75. Which role is responsible for the overall project success?
Executive
Project Manager
Senior User
Senior Supplier
✅ Correct Answer: Executive
76. What is the purpose of the "Risk Management Approach"?
To define how risks will be managed
To track daily issues
To define stakeholder roles
To authorize work packages
✅ Correct Answer: To define how risks will be managed
77. Which PRINCE2 document records all identified risks?
Risk Register
Issue Register
Lessons Log
Daily Log
✅ Correct Answer: Risk Register
78. What is the purpose of the "Quality Management Approach"?
To define quality expectations and controls
To track project risks
To manage stakeholder communications
To authorize work packages
✅ Correct Answer: To define quality expectations and controls
79. Which PRINCE2 principle ensures that projects are managed by exception?
Manage by Exception
Learn from Experience
Focus on Products
Tailor to Suit the Project
✅ Correct Answer: Manage by Exception
80. What is the purpose of the "Issue Register"?
To track project issues and changes
To define stakeholder roles
To manage risks
To authorize work packages
✅ Correct Answer: To track project issues and changes
The Prince2 Practitioner Pr2p certification is a globally recognized credential for IT professionals.
This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.
Want more practice? Check out our other mock exams: