1. What is the primary goal of SAP Activate methodology?
To provide a guided approach to SAP implementation
To replace Agile methodologies
To create detailed project documentation
To automate all SAP processes
✅ Correct Answer: To provide a guided approach to SAP implementation
2. Which phase in SAP Activate methodology involves solution validation?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Explore
3. What are the key components of SAP Activate methodology?
Agile, Waterfall, and SAP ERP
SAP Best Practices, Guided Configuration, and Agile Methodology
Scrum, Kanban, and Lean
Design Thinking, Prototyping, and Go-Live
✅ Correct Answer: SAP Best Practices, Guided Configuration, and Agile Methodology
4. During which phase of SAP Activate does the initial project planning occur?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Prepare
5. What is the purpose of the Realize phase in SAP Activate?
To build and test the solution
To go live with the new system
To validate the business case
To plan the deployment strategy
✅ Correct Answer: To build and test the solution
6. Which of the following is NOT a phase in SAP Activate?
Prepare
Execute
Explore
Run
✅ Correct Answer: Execute
7. What is the main benefit of using SAP Best Practices in an implementation project?
It eliminates the need for system testing
It accelerates project timelines and reduces risk
It replaces the need for business process mapping
It provides a fixed, unchangeable template
✅ Correct Answer: It accelerates project timelines and reduces risk
8. Which tool is primarily used for Guided Configuration in SAP Activate?
Solution Manager
SAP Fiori
SAP Cloud ALM
SAP Implementation Cockpit
✅ Correct Answer: SAP Implementation Cockpit
9. What is a key characteristic of Agile methodology within SAP Activate?
Fixed scope and detailed design before development
Iterative development with continuous feedback
A single development cycle before testing
Only applicable for on-premise deployments
✅ Correct Answer: Iterative development with continuous feedback
10. Which phase in SAP Activate methodology focuses on end-user training and system readiness?
Prepare
Explore
Deploy
Realize
✅ Correct Answer: Deploy
11. What type of testing is commonly performed during the Realize phase?
Unit Testing
Business Case Validation
User Training
Deployment Readiness Check
✅ Correct Answer: Unit Testing
12. What is the outcome of the Explore phase in SAP Activate?
A detailed project timeline
A validated system configuration
A completed go-live checklist
A fully implemented system
✅ Correct Answer: A validated system configuration
13. Which phase in SAP Activate ensures that all technical and functional elements are ready for system go-live?
Prepare
Deploy
Explore
Realize
✅ Correct Answer: Deploy
14. What is the main focus of the Run phase in SAP Activate?
Continuous improvements and system operations
Final system testing
End-user training
Data migration
✅ Correct Answer: Continuous improvements and system operations
15. What methodology does SAP Activate replace?
SAP ASAP
Six Sigma
PRINCE2
Scrum
✅ Correct Answer: SAP ASAP
16. What is one of the first deliverables in the Prepare phase?
System Go-Live Checklist
Project Charter
End-User Training Plan
Solution Blueprint
✅ Correct Answer: Project Charter
17. Which of the following is an essential activity in the Deploy phase?
Data migration and cutover
System blueprinting
Agile backlog refinement
Developing custom reports
✅ Correct Answer: Data migration and cutover
18. What is a key role of business users in the Explore phase?
Providing feedback on fit-gap analysis
Executing final system testing
Developing ABAP code
Defining project timelines
✅ Correct Answer: Providing feedback on fit-gap analysis
19. Which tool supports the agile implementation approach of SAP Activate?
SAP Solution Manager
SAP BW
SAP GUI
SAP ECC
✅ Correct Answer: SAP Solution Manager
20. Which SAP Activate phase includes the execution of Fit-to-Standard workshops?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Explore
21. Which SAP Activate phase includes the creation of a project roadmap?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Prepare
22. What is the purpose of the SAP Activate Methodology Explorer?
To provide access to accelerators and templates
To replace SAP Solution Manager
To automate code development
To manage user licenses
✅ Correct Answer: To provide access to accelerators and templates
23. Which deliverable is created during the Explore phase?
Fit-Gap Analysis Report
Technical Specification Document
User Training Materials
Go-Live Approval
✅ Correct Answer: Fit-Gap Analysis Report
24. What is the recommended approach for testing in SAP Activate?
Continuous testing throughout the project
Only end-to-end testing before go-live
No testing required for cloud implementations
User acceptance testing only
✅ Correct Answer: Continuous testing throughout the project
25. Which tool is used for agile project management in SAP Activate?
SAP Cloud ALM
SAP ERP
SAP BW
SAP GUI
✅ Correct Answer: SAP Cloud ALM
26. What is the purpose of the SAP Activate Roadmap Viewer?
To visualize project phases and tasks
To monitor system performance
To create financial reports
To manage user authorizations
✅ Correct Answer: To visualize project phases and tasks
27. Which activity occurs during the Prepare phase?
Team onboarding and kickoff
System configuration
User training
Data migration
✅ Correct Answer: Team onboarding and kickoff
28. What is the primary focus of SAP Best Practices?
Predefined business processes
Custom development guidelines
Hardware specifications
User interface design
✅ Correct Answer: Predefined business processes
29. Which document is typically finalized during the Realize phase?
Test Scripts
Project Charter
Business Case
Training Plan
✅ Correct Answer: Test Scripts
30. What is the purpose of the SAP Activate Agile Toolkit?
To support agile project execution
To replace SAP Fiori apps
To automate financial closing
To manage infrastructure
✅ Correct Answer: To support agile project execution
31. Which team is typically involved in Fit-to-Standard workshops?
Business Process Owners
Infrastructure Team
Security Team
Training Team
✅ Correct Answer: Business Process Owners
32. What is the recommended approach for data migration in SAP Activate?
Iterative and parallel with configuration
Single upload after go-live
Manual entry only
No data migration needed
✅ Correct Answer: Iterative and parallel with configuration
33. Which phase includes the preparation of cutover activities?
Deploy
Explore
Prepare
Realize
✅ Correct Answer: Deploy
34. What is the purpose of the SAP Activate Community?
To share knowledge and best practices
To provide technical support
To manage licenses
To host development environments
✅ Correct Answer: To share knowledge and best practices
35. Which testing type is typically performed last?
User Acceptance Testing
Unit Testing
Integration Testing
Performance Testing
✅ Correct Answer: User Acceptance Testing
36. What is the purpose of the SAP Activate Quality Gates?
To ensure phase completion criteria are met
To manage user access
To monitor system performance
To create financial reports
✅ Correct Answer: To ensure phase completion criteria are met
37. Which activity is part of the Run phase?
Continuous improvement
System configuration
Project planning
Blueprinting
✅ Correct Answer: Continuous improvement
38. What is the recommended team structure in SAP Activate?
Cross-functional teams
Siloed departments
External consultants only
No formal structure
✅ Correct Answer: Cross-functional teams
39. Which deliverable is created during the Prepare phase?
Project Management Plan
Technical Design Documents
Training Materials
Test Cases
✅ Correct Answer: Project Management Plan
40. What is the purpose of the SAP Activate Playbooks?
To provide step-by-step implementation guidance
To replace SAP Best Practices
To automate testing
To manage cloud infrastructure
✅ Correct Answer: To provide step-by-step implementation guidance
41. Which tool is used for collaboration in SAP Activate projects?
SAP Cloud ALM
SAP ERP
SAP BW
SAP GUI
✅ Correct Answer: SAP Cloud ALM
42. What is the recommended approach for change management in SAP Activate?
Continuous engagement with stakeholders
Implemented after go-live
Limited to technical changes only
Not required for cloud projects
✅ Correct Answer: Continuous engagement with stakeholders
43. Which phase includes the preparation of training materials?
Realize
Prepare
Explore
Deploy
✅ Correct Answer: Realize
44. What is the purpose of the SAP Activate Task Manager?
To track project activities
To monitor system performance
To create financial reports
To manage user licenses
✅ Correct Answer: To track project activities
45. Which methodology does SAP Activate combine?
Agile, Waterfall and Lean
Six Sigma only
PRINCE2 only
Scrum only
✅ Correct Answer: Agile, Waterfall and Lean
46. What is the purpose of the SAP Activate Content Library?
To access preconfigured content
To store custom code
To manage user access
To host training videos
✅ Correct Answer: To access preconfigured content
47. Which testing approach is recommended in SAP Activate?
Test-driven development
No testing needed for cloud
Only integration testing
Manual testing only
✅ Correct Answer: Test-driven development
48. What is the purpose of the SAP Activate Adoption Dashboard?
To measure project progress and adoption
To monitor system performance
To create financial reports
To manage infrastructure
✅ Correct Answer: To measure project progress and adoption
49. Which phase includes the validation of the business case?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Prepare
50. What is the purpose of the SAP Activate Migration Cockpit?
To support data migration
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To support data migration
51. Which SAP Activate phase includes the creation of a test strategy?
Prepare
Explore
Realize
Deploy
✅ Correct Answer: Prepare
52. What is the purpose of the SAP Activate Configuration Workbook?
To document system configuration decisions
To track project budget
To manage user training
To monitor system performance
✅ Correct Answer: To document system configuration decisions
53. Which activity occurs during the Explore phase?
Solution demonstration
Data migration execution
User training delivery
Go-live approval
✅ Correct Answer: Solution demonstration
54. What is the recommended approach for scope management in SAP Activate?
Prioritized backlog with iterative refinement
Fixed scope throughout project
No formal scope management
Scope changes only after go-live
✅ Correct Answer: Prioritized backlog with iterative refinement
55. Which tool is used for requirements management in SAP Activate?
SAP Cloud ALM
SAP Fiori
SAP BW
SAP GUI
✅ Correct Answer: SAP Cloud ALM
56. What is the purpose of the SAP Activate Issue Manager?
To track and resolve project issues
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To track and resolve project issues
57. Which document is typically created during the Deploy phase?
Cutover Plan
Project Charter
Business Blueprint
Test Strategy
✅ Correct Answer: Cutover Plan
58. What is the purpose of the SAP Activate Risk Manager?
To identify and mitigate project risks
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To identify and mitigate project risks
59. Which phase includes the execution of integration tests?
Realize
Prepare
Explore
Deploy
✅ Correct Answer: Realize
60. What is the purpose of the SAP Activate Business Process Hierarchy?
To organize business processes for implementation
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To organize business processes for implementation
61. Which activity occurs during the Run phase?
Post-go-live support
System configuration
Project planning
Blueprinting
✅ Correct Answer: Post-go-live support
62. What is the purpose of the SAP Activate Scope Item Catalog?
To select predefined business processes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To select predefined business processes
63. Which document is typically created during the Realize phase?
Technical Design Document
Project Charter
Business Case
Training Plan
✅ Correct Answer: Technical Design Document
64. What is the purpose of the SAP Activate Business Scenario Recommendations?
To suggest relevant business processes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To suggest relevant business processes
65. Which phase includes the execution of performance tests?
Realize
Prepare
Explore
Deploy
✅ Correct Answer: Realize
66. What is the purpose of the SAP Activate Process Flow Diagrams?
To visualize end-to-end processes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To visualize end-to-end processes
67. Which activity occurs during the Prepare phase?
Project governance setup
System configuration
User training
Data migration
✅ Correct Answer: Project governance setup
68. What is the purpose of the SAP Activate Configuration Questionnaire?
To gather system configuration requirements
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To gather system configuration requirements
69. Which document is typically created during the Explore phase?
Solution Scope Document
Project Charter
Technical Design Document
Test Scripts
✅ Correct Answer: Solution Scope Document
70. What is the purpose of the SAP Activate Test Case Catalog?
To provide predefined test cases
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To provide predefined test cases
71. Which phase includes the preparation of user documentation?
Realize
Prepare
Explore
Deploy
✅ Correct Answer: Realize
72. What is the purpose of the SAP Activate Business Process Change Register?
To track process changes during implementation
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To track process changes during implementation
73. Which activity occurs during the Deploy phase?
System readiness check
System configuration
Project planning
Blueprinting
✅ Correct Answer: System readiness check
74. What is the purpose of the SAP Activate Business Process Test Scripts?
To validate configured business processes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To validate configured business processes
75. Which document is typically created during the Prepare phase?
Communication Plan
Technical Design Document
Test Scripts
User Manual
✅ Correct Answer: Communication Plan
76. What is the purpose of the SAP Activate Business Process Test Results?
To document testing outcomes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To document testing outcomes
77. Which phase includes the execution of security tests?
Realize
Prepare
Explore
Deploy
✅ Correct Answer: Realize
78. What is the purpose of the SAP Activate Business Process Test Plan?
To organize testing activities
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To organize testing activities
79. Which activity occurs during the Run phase?
Incident management
System configuration
Project planning
Blueprinting
✅ Correct Answer: Incident management
80. What is the purpose of the SAP Activate Business Process Test Data?
To support testing of business processes
To manage user access
To create financial reports
To monitor system performance
✅ Correct Answer: To support testing of business processes
The Sap Activate Project Manager certification is a globally recognized credential for IT professionals.
This practice test helps you prepare by covering key topics like hardware, networking, troubleshooting, and security.
Want more practice? Check out our other mock exams: